1. PROJECT: City of Laredo Rehabilitation of Manholes and Sewer Cleaning 12/1/2010 completed
    AMOUNT: $1,200,000.00
    SCOPE: Rehab 67 manholes and CCTV and Clean 56,000 LF of major trunks lines 24"-42"
    1.25 mile long bypass pumping trunk line in one section 3-12" Godwin Pumps
    Contact: Oscar Martel Project Engineer E.I.T.
  2. Picture of project Picture of project Picture of project
  3. PROJECT: City of Laredo Rehabilitation of Manholes Phase V 11/1/2011 completed
    AMOUNT: $300,000.00
    SCOPE: Rehab 85 60-40 year old brick and precast manholes Special internal bypass was used to keep sewer in service during application
    Contact: Oscar Martel Project Engineer E.I.T.
  4. Picture of project Picture of project Picture of project
  5. PROJECT: City of Pharr Manhole Rehab of Precast and Brick 10/1/2010 completed
    AMOUNT: $20,000.00
    SCOPE: Rehab brick and precast leaking Manholes
    Contact: Eddie Deleon Waste Water Superintendent
  6. Picture of project Picture of project Picture of project
  7. PROJECT: Mercedes American Recovery Reinvestment Act Rehab Project  5/1/2011
    AMOUNT: $45,000.00
    SCOPE: Rehab Various Manholes and Lift Stations with Manhole Mortar and Epoxy
    Contact: Felipe Fernandez Inspector for T.W.B.D.
  8. Picture of project Picture of project Picture of project
  9. PROJECT: City of Houston Epoxy and Manhole Mortar Demo
    AMOUNT: Demo
    SCOPE: Rehab brick and precast manholes in the downtown City of Houston Sewer System
    Contact: Jason Iken Dept. of Public Works
  10. Picture of project Picture of project Picture of project
  11. Project: City of Zapata Rehabilitation of 23 Lift Stations 2011
    Amount: $42,000-Ongoing procurement maintenance program
    Scope:  Lift Station Assessment and Rehab with Manhole Mortar and 100% Solids Epoxy
    Lift Station grit removal of 30’ and 40’ deep lift stations
    Contact: Manuel Gonzalez Jr., P.E., S.I.T. City Engineer
  12. Picture of project Picture of project Picture of project
  13. Project: City of Mercedes on Federal ARRA
    Amount: $47,000
    Scope:  Rehab manholes and lift stations throughout the City using approved equal Manhole Mortar™ and Epoxy  Made in the USA Approved Products
    Contact: Marcelo Cosme Wastewater Operations CH2MHill and Alfredo Resendez P.E.
  14. Picture of project Picture of project Picture of project
  15. Project: City of Harlingen New WWTP Headworks Epoxy Coating
    Amount: $79,000
    Scope:  Coat 10,000 Sq Ft of brand new exposed concrete inside WWTP headworks with 100% Solids Epoxy Contact: Jim Vallely Head of Wastewater for Harlingen
    Contact: Jim Vallely Head of Wastewater for Harlingen
  16. Picture of project Picture of project
  17. Project: City of Mercedes Clarifier Rehab and Protective Coatings
    Amount: $35,000
    Scope:  Rehab one 65’ Diameter Clarifier and one 85’ Diameter Clarifier
    Contact: Marcelo Cosme Wastewater Operations CH2MHill and Alfredo Resendez P.E.
  18. Picture of project Picture of project Picture of project
  19. Project: City of Conroe Fiber Glass Manhole Inserts
    Amount: $49,000
    Scope:  Installed 7 fiberglass Inserts on 15” forcemain discharge without bypass pumping (kept in service the entire project)
    Contact: Jason Miller Head of Wastewater Maintenance Department
  20. Picture of project Picture of project Picture of project
  21. Project: City of Harlingen Lift Station Rehab
    Amount: $14,000
    Scope:  Shotcrete 1-2” of Manhole MortarTM to deteriorated concrete walls and install Epoxy protective coating
    Contact: Jim Vallely Head of Wastewater for Harlingen Water Works
  22. Picture of project Picture of project Picture of project

Training Course Overview

The trainee will be shown how to operate, maintain, apply repair coatings, and repair sewer structures such as manholes, lift stations, and other various sewer structures.

Training shall include 40 hours of the following:

  1. How to prepare and clean the surface prior to applying coatings
  2. Identifying needed repairs and how to fix them
  3. How to operate equipment: Mortar mixer, mortar pump, spray nozzle
  4. How to maintain all equipment
  5. How to property mix materials to correct design
  6. Confined space and Safety training course is offer in addition if the applicator does not already have a certification.

Applicator training can be done by actual hands on field training provide that proper insurance requirements are met, field observation, and/or at any facility we can demonstrate all the field functions. Applicator will be given all equipment technical manuals and maintenance procedures. Applicator will be given a full parts list with cost for replacement. Applicator will also be given a certificate of completion once they have completed the 40 hour course and are able to demonstrate the ability reproduce the correct procedures in a successful application of these products. For more information please contact Eric Dupre’ Training and technical Coordinator.


Become an Applicator